16 men + 12 women complete the work in 8 days.
20 men complete the work in 16 days.
∴ 16×8 men + 12×8 women ≡20×16men
=> 128 men + 96 women ≡ 320 men
=> 96 women => 192 men
=> 1 woman = 2 men
∴ 16 women = 32 men
∴ M1\D1 = M2\D2
=> 20×16 = 32×D2
=>D2 = 20×16\32 = 10 days