Explanation:
Ram’s 3 days work = 3×1\12=3\12=1\4
Remaining work = 1−1\4=3\4
Ram and Ravi’s one day work = 1\12+1\21=7+4\84=11\84
11\84 part of work will be done by Ram and Ravi m one day.
3\4 part of work
= 84\11×3\4=63\11=5 8\11 days
Total no. of days = 3+5 8\11=8 8\11 days