P complete 1\4th work in 10 days.
So P will complete the whole work in 40 days
Q Completes (40%= 2\5)th work in 40 days
Q will complete the whole work in 40×5\ 2 =100 days
R complete in 13 days.
R will complete whole work in 39 days.
Work will be finished firstly by the man who will take less days to complete it, So R will complete it first.