Explanation:
In 10 days, Ken had completed 40% of the job.
Therefore, he would complete 40\10 = 4% of the work in a day.
As Jacob is 50% as efficient as Ken, he would complete 2% of the work in a day.
Working together they will complete 4 + 2 = 6% of the work in a day.
To complete the balance 60% of the job, they will take 60\6 = 10 more days.
Hence, the task will be completed in 20 days.