Explanation:
(6m+8b)×10 days
=(26m+48b)×2 days
[m1×t1×d1\w1=m2×t2×d2\w2]
30m+40b=26m+48b
4m = 8b
m = 2b
m\b=2\1
1m (work) = 2 units/day
1b (work) = 1 units/day
Hence,
Total work
=(6×2+8×1)×10
=200 units
Required Time
(15m+20b)
=200\(15×2+20×1)=200\50=4 days