Explanation:
According to question,
Total work=12M×12D=144units
Work done by 12 men in 6 days
=12×6=72units
Rest work=144−72=72units
Required time for 6 men to complete the work
=72\6=12days
Hence,
Total Time=12+6=18days
Extra Time=18−12=6days