Explanation:
A can do the work in 6 days.
A’s one day work = 1\6 part.
B’s one day work = 1\8 part
C’s one day work = 1\12 part
(B+C)’s one day work = 1\8+1\12=3+2\24=5\24
(B+C)’s 2 day work = 5\24×2=5\12
Remaining work = 1−5\12=7\12
Remaining work is done by A and B
(A+B)’s one day work = 1\6+1\8=4+3\24=7\24
7\12 part of work can be done by
A and B in = 7\12×24\7=2 days
The work is completed in 2+2 = 4 days.