Explanation:
A’s one day work = 1\32
A’s 4 days work = 1\32×4=1\8
Remaining part = 1−1\8=7\8
Since work was to be completed in 24 days, Remaining days=24-4=20 days
(A+B)’s 20 days work = 7\8
(A+B)’s one day’s work = 7\8×1\20=7\160
B’s one day’s work = 7\60−1\32=7−5\160=2\160=1\80
B can finish the work in 80 days.