A can do 1\2 of a piece of work in 5 days
A can do 1 unit of the work in
5×2 \1 = 10 days
Similarly B complete 1 unit of
=9×5,\3 = 15days
C complete 1 unit of work in
=8× 3\2=12 days
=A+B+C one day work
=15 units
They will complete the whole work in
60\15=4 days