Case 1: If A begins, then the work will take:
Total number of days = (x+x\y) days
Case 2: If B begins,
Total number of days = x + 1 days
By applying this rule, if A begins, the work will be completed
= (6+6\8) days. That is, (27\4)
= 6 3\4 days