Explanation:
A and B together can complete the work in 12 days. They work for 5 days. So 7 days work of A + B is left and which is done by A in 14 days.
According to question,
(A+B)7=A×14
7A+7B=14A
7B=7A
A : B = 1 : 1
Now,(A+B)12=A×D
(1+1)12=1×D
D = 24 days