Explanation:
60 men work for 200 days.They stops for 10 day due to bad weather.so the work is to complete in
(50−10)=40 days in order to complete in schedule time i.e 250 days.
Let ‘n’ number of more man is required
(60men×200days)+(60+n)men×40days
=60men×250days
12000+(60+n)men×40days
=15000
(60+n)40=3000
60+n=75
n=15