5M×6 days=10W×5 days
3M = 5W
M\W=5\3
m\b=2\1
1M (work) = 5 units/day
1W (work) = 3 units/day
Hence,
Total work
=(5M×6)=5×5×6
=150 units
Required Time for
(5M+3W)
=Total work\ Work done/day
150\ (5×3+3×5)=150\ 30=5 days